Containerized Energy Storage System — Single Charge-Discharge Cycle Energy Link and Auxiliary Power Consumption Analysis Report
This report analyzes the energy link for a complete SOC 0% → 95% → 0% cycle of the D-Ocean-5016D containerized energy storage system (12 clusters × 418 kWh, Hihtium 314 Ah cells 1P416S). The system uses the Envicool EMW600HCNC3E air-cooled chiller (CE-certified / C5-M anti-corrosion), and the auxiliary equipment draws power directly from the main circuit + UPS + distribution box (DC 24 V/48 V).
- Core RTE (25°C ideal conditions) = 88.48% (including step-up transformer 0.99² × PCS 0.98² × battery DC RTE 0.94)
- Electrical auxiliary system (14 items per the project's actual electrical design; see Section 1.1 for details): 7.25 kW fixed continuous operation, consuming 13.0 – 14.7 kWh per cycle
- System net RTE range at 0.5P full-power operation: 85.88% – 87.97% (maximum power to liquid cooling shutdown)
- Liquid cooling self-circulation 0.74 kW consumes about 1.5 kWh per cycle; rated cooling 27.8 kW consumes about 57.5 kWh per cycle
- 88.5% net RTE is unachievable in this model (maximum is 87.97%); 87% net RTE control target: cooling duty cycle ≤ 48.3%
- Container continuous auxiliary total power 7.25 kW, peak (including maximum liquid cooling power) 37.25 kW
1. System Parameters
| Parameter | Value | Unit |
|---|---|---|
| Number of clusters | 12 | — |
| Rated capacity per cluster | 418 | kWh |
| Total system capacity @DC | 5016 | kWh |
| System nominal power | 2500 | kW |
| System continuous operating power (0.5P estimate) | ≈ 2500 | kW |
| Depth of discharge (DoD) | 95 | % |
| Usable battery energy | 4765.2 | kWh |
| PCS charging efficiency | 98.0 | % |
| PCS discharging efficiency | 98.0 | % |
| Battery DC round-trip efficiency | 94.0 | % |
| Step-up transformer efficiency (one-way) | 99.0 | % |
| Step-up transformer efficiency (two-way = 0.99²) | 98.01 | % |
1.1 Electrical Auxiliary System Architecture
D-Ocean-5016D project actual electrical design load list (from engineering distribution diagram):
| Level | Component | Quantity | Unit Power | Total Power | Remarks |
|---|---|---|---|---|---|
| Cluster-level (12 sets) | High-voltage box AC-DC SMPS | 12 | 350 W | 4 200 W | AC priority, outputs 24 V for whole cluster BMS/BMU |
| Cluster-level | High-voltage box DC-DC SMPS | 12 | 200 W | — | Switches in when AC fails; 200 W backup per cluster |
| Whole container (1 set) | Distribution box 24 V SMPS | 1 | 480 W | 480 W | Container-level 24 V main bus (DC) |
| Whole container | Distribution box 48 V SMPS | 1 | 120 W | 120 W | Container-level 48 V bus (DC) |
| Whole container | Industrial air conditioner | 1 | 240 W | 240 W | Control cabinet cooling, continuous operation |
| Whole container | Dehumidifier | 6 | 130 W | 780 W | Nominal 120 W, actual 130 W |
| Whole container | Emergency lighting | 1 | 50 W | 50 W | Continuous operation |
| Whole container | Cooling fan | 1 | 50 W | 50 W | Continuous operation |
| Whole container | Screen (ITAV industrial display) | 1 | 50 W | 50 W | Continuous operation (EMS HMI) |
| UPS items | Fire host K11031M2 | 1 | 200 W | 200 W | 230 VAC continuous monitoring |
| UPS items | Video surveillance power supply | 1 | 240 W | 240 W | UPS backed up |
| UPS items | 24 V auxiliary power supply | 1 | 120 W | 120 W | UPS backed up |
| UPS items | 1~12# BMS power supply | 12 | 60 W | 720 W | 60 W per cluster |
| UPS items | Explosion-proof exhaust fan CNF-350A | 1 | 240 W | — | UPS backed up, only on alarm |
| UPS items | Maintenance socket | 1 | 1000 W | — | Peak reservation, not continuous |
| UPS items | Spare and socket | 1 | 1000 W | — | Peak reservation, not continuous |
| Fixed auxiliary total | — | — | — | 7 250 W ≈ 7.25 kW | Normal AC mode, excluding transients |
Architecture notes:
- The high-voltage box SMPS outputs 24 V DC to power the whole-cluster contactors/control/heating, etc.; the AC-DC 350 W is the main power supply, and the DC-DC 200 W is only switched in when AC fails.
- The distribution box SMPS supplies the container-level 24 V/48 V bus (not UPS-backed), powering the main circuit loads.
- Six AC dehumidifiers GCH-8120S (130 W actual power) are powered from the main circuit, continuous operation.
- 12 cluster BMS power supplies (60 W/cluster) are UPS-backed, ensuring the BMS continues to operate and report alarms during power loss.
- Fire host 200 W is UPS-backed (continuous monitoring); explosion-proof exhaust fan 240 W is only started by UPS backup on alarm (transient about 3 seconds).
- Maintenance socket and spare socket are rated at 1 kW peak reservation, not counted in RTE continuous auxiliary.
- The electrical auxiliary system above does not include the emergency water firefighting main circuit (fire pumps, sprinklers, etc.). Actual projects equipped with an emergency water system must supplement per EN 12845 (typically 5 – 10 kW including fire pumps), and the container main breaker margin must be verified.
2. Wiring and Terminals
This section does not involve external wiring; it focuses on energy metering points, suggested as follows:
- Grid-side metering: bidirectional meter at the outlet end of the grid-connection switch, as the statistical source for / .
- PCS AC-side metering: bidirectional meter for verifying the PCS's own efficiency.
- Battery DC-side: BMS DC bus sampling for calculating battery DC round-trip efficiency.
- Auxiliary branch: liquid cooling unit, BMS/EMS, and dehumidifier supply circuits should be metered separately to facilitate auxiliary power consumption traceability.
Warning
The liquid cooling unit EMW600HCNC3E has a maximum working current of 72 A and a power supply of 380-415 V 3~. Before maintenance, the upstream breaker must be disconnected and locked out; the coolant is 50% ethylene glycol aqueous solution (containing R32 refrigerant circuit). Open flames are prohibited, and protective gloves must be worn.
3. Liquid Cooling Unit Specifications (EMW600HCNC3E)
| Parameter | Value | Unit |
|---|---|---|
| Cooling capacity @W18/L35 | 60 | kW |
| Cooling input power @W18/L35 | 27.8 | kW |
| Heating capacity @Tu=10°C | 24 | kW |
| Heating input power @Tu=10°C | 24 | kW |
| Self-circulation (pump only) power | 0.74 | kW |
| Maximum consumption power | 30.0 | kW |
| Outlet water temperature | 18 | °C |
| Rated circulation flow | 500 @ 150 kPa | L/min |
| Operating ambient temperature | -30 ~ +55 | °C |
| Anti-corrosion grade | C5-M | — |
| Refrigerant | R32 | — |
| Coolant | 50% ethylene glycol aqueous solution | — |
| Power supply | 380-415 V 3~ 50/60 Hz | — |
| Maximum working current | 72 | A |
| Dimensions (W×D×H) | 1200 × 440 × 2400 | mm |
| Weight (excluding coolant) | 471 | kg |
| Noise level | ≤80 | dB(A) |
| Protection grade | IPX5 | — |
| Special configuration | Dual refrigeration systems (fault backup) / RS485 communication | — |
3.1 Working Mode Control Logic (BMS active, reference Envicool platform general control)
| Mode | Start Condition | Stop Condition | Outlet Liquid Temp. Setting | Remarks |
|---|---|---|---|---|
| Cooling | 18 °C (configurable) | Hysteresis 3 °C | ||
| Heating | 20 °C (configurable) | Hysteresis 5 °C | ||
| Self-circulating | — | Pump only, 0.74 kW |
Note: The EMW600HCNC3E specification sheet does not disclose a detailed control logic table. The temperature thresholds above are general reference values for the Envicool platform; actual projects must follow the D-Ocean-5016D BMS integration specifications.
3.2 BMS Power-loss Protection Logic (BMS inactive)
| Mode | Start Condition | Duration | Trigger Purpose |
|---|---|---|---|
| Forced self-circulation (high temperature) | 120 s | Prevent battery overheating | |
| Forced self-circulation (low temperature) | 120 s | Prevent pipeline condensation/freezing |
3.3 Mode Priority
Cooling > Heating > Self-circulation; forced protection conditions (3.2) can override the above priority and directly enter self-circulation.
4. Communication
This report does not cover external communication protocols, but it is recommended to unify the following interfaces and data points during on-site data acquisition to facilitate EMS upper-level RTE calculation:
- BMS → EMS: 12 clusters DC voltage/current, SOC, SOH, cell maximum/minimum temperature.
- PCS → EMS: AC-side voltage/current/power, charge/discharge state, fault word, efficiency curve.
- Liquid cooling unit → EMS: outlet liquid temperature, compressor/pump/fan start-stop, current mode (cooling/heating/self-circulation), fault word.
- Auxiliary branch meter → EMS: main circuit auxiliary branch total meter (for calculating total auxiliary consumption), UPS output itemized meter, BMS/EMS DC side, dehumidifier branch.
Tip
The liquid cooling unit's "cooling/heating/self-circulation" status word must be reported to EMS; otherwise, the RTE calculation cannot distinguish between self-circulation and cooling duty cycle, causing deviations exceeding 1 percentage point.
5. Operating Steps and Calculation Basis
5.1 Baseline Link Energy
- Battery DC round-trip efficiency 94%, symmetrically split as 96.96% × 96.96%
- PCS charge/discharge efficiency both 98.0%
- Step-up transformer efficiency (step-up + step-down) 0.99 × 0.99 = 0.9801 (two-way)
- DoD = 95%
System theoretical efficiency excluding liquid cooling and fixed auxiliary consumption (core of PCS + battery + step-up transformer, 25°C ideal conditions):
5.2 Single-Cycle Energy Link
- Charging path: grid → step-up transformer (×99.0%) → PCS (×98.0%) → battery DC (×96.96%) → stored 4765.2 kWh.
- Discharging path: battery DC (×96.96%) → PCS (×98.0%) → step-up transformer (×99.0%) → AC gross output 4482.0 kWh.
- Liquid cooling and auxiliary consumption are presented as floating branches: charging side adds auxiliary consumption; discharging side deducts auxiliary consumption from PCS gross output.
5.3 General Formulas
Let cooling duty cycle (self-circulation duty cycle ), based on 0.5P continuous operating power :
- Charging time
- Discharging time
Fixed auxiliary power (project actual electrical design list, see Section 1.1 for details).
Closed-form after substitution (eliminating the intermediate variable):
5.4 Auxiliary Power Consumption Scenarios
Fixed auxiliary consumption per Section 1.1 actual electrical design: 12 cluster high-voltage boxes 4.2 kW + distribution box 0.6 kW + 6 dehumidifiers 0.78 kW + industrial air conditioner 0.24 kW + emergency lighting/cooling/HMI screen 0.15 kW + 12 cluster BMS power supplies 0.72 kW + fire host 0.20 kW + video surveillance 0.24 kW + 24 V auxiliary 0.12 kW, totaling . Liquid cooling unit modeled in 8 typical states:
| Liquid Cooling State | (kW) | (kW) | (kWh) | (kWh) | (kWh) | (kWh) | RTE (%) |
|---|---|---|---|---|---|---|---|
| Liquid cooling off | 0.00 | 7.25 | 14.69 | 5080.39 | 13.00 | 4469.00 | 87.97 |
| Self-circulation | 0.74 | 7.99 | 16.19 | 5081.89 | 14.33 | 4467.67 | 87.89 |
| 25% cooling | 6.95 | 14.20 | 28.77 | 5094.47 | 25.46 | 4456.54 | 87.48 |
| 50% cooling | 13.90 | 21.15 | 42.85 | 5108.55 | 37.92 | 4444.08 | 86.99 |
| 75% cooling | 20.85 | 28.10 | 56.93 | 5122.63 | 50.39 | 4431.61 | 86.51 |
| Rated cooling | 27.80 | 35.05 | 71.01 | 5136.71 | 62.84 | 4419.16 | 86.04 |
| Rated heating | 24.00 | 31.25 | 63.31 | 5129.01 | 56.04 | 4425.96 | 86.31 |
| Maximum power | 30.00 | 37.25 | 75.47 | 5141.17 | 66.79 | 4415.21 | 85.88 |
Note: In the scenario table, the for 25%/50%/75% cooling is linearly interpolated based on the rated cooling power of 27.8 kW (excluding the self-circulation floor of 0.74 kW), which slightly differs from the Section 5.3 formula ; for strict consistency, it is recommended to use the Section 5.3 formula + explicit duty cycle as input.
AC failure boundary case: When all 12 cluster high-voltage boxes switch to DC-DC 200 W backup, fixed auxiliary becomes , corresponding RTE slightly higher than this table (about 88.7% when liquid cooling is off); however, this is an emergency condition, and normal RTE protocols are based on AC mode.
Fire alarm transient: When H₂ detector or smoke/heat sensor triggers, the fire host enters alarm state, the explosion-proof exhaust fan (240 W) starts, and transient auxiliary power jumps up by ~240 W (about 3 seconds); the impact on RTE statistics is negligible.
5.5 Conclusions and Recommendations
- Core RTE (25°C most ideal conditions) = 88.48% (step-up transformer 0.99² × PCS 0.98² × battery DC RTE 0.94). This value is the theoretical upper limit, corresponding to ambient temperature 25°C, battery optimal working temperature, no auxiliary consumption, no standby, SoH=100% extreme ideal conditions.
- After including 7.25 kW fixed auxiliary (project actual electrical design list), net RTE is 87.97% with liquid cooling off; 87.89% with liquid cooling self-circulation; 86.99% at 50% cooling duty cycle; 86.04% at rated cooling.
- 88.5% net RTE is unachievable in this model: even with liquid cooling completely off + 25°C ideal conditions + 7.25 kW fixed auxiliary, net RTE can only reach 87.97%; the theoretical core upper limit of 88.48% requires simultaneously eliminating all auxiliary consumption (infeasible).
- 87% net RTE control target: From :
i.e., cooling duty cycle must be ≤ 48.3% (approximately corresponding to the lower edge of the 50% cooling scenario), liquid cooling single-cycle average power must be ≤ 13.81 kW.
- Typical operating range (25°C ideal): net RTE 86.5% – 88.0% (covering 25% – 75% cooling), single-cycle AC-side output 4432 – 4457 kWh. Actual field RTE is usually below this range due to ambient temperature, battery temperature rise, auxiliary fluctuation, and other factors.
- Electrical auxiliary system total power 7.25 kW is one of the main RTE burdens: single-cycle fixed consumption 13.0 – 14.7 kWh, already exceeding self-circulation liquid cooling (1.5 kWh) by an order of magnitude. Optimizing 12 cluster high-voltage box SMPS efficiency (350 W → 280 W) can recover about 0.4 percentage points RTE.
- Liquid cooling remains the dominant RTE term: single-cycle liquid cooling consumption 1.5 kWh (self-circulation) – 57.5 kWh (rated cooling); fixed auxiliary about 13 kWh, liquid cooling + fixed auxiliary RTE loss contribution ratio is approximately 75% / 25%.
- Six dehumidifiers consume significant power: 0.78 kW accounts for 10.8% of total auxiliary, single-cycle consumption 1.58 kWh. It is recommended to evaluate dehumidification necessity (decide start/stop based on ambient humidity sensor data); on-demand operation can recover about 0.2 percentage points RTE.
- Technical protocol recommendations: clarify RTE measurement point (recommend grid-side bidirectional meter), whether to include liquid cooling/fire protection/standby/sockets, test temperature range (baseline 25°C), SOC window (0-95%), auxiliary metering method (recommend SMPS branch + fire host + 12 cluster BMS separately metered, facilitating traceability per Section 1.1 architecture).
5.6 Container Main Breaker Load Verification
Based on the continuous/peak total power statistics from the Section 1.1 table:
| Mode | (kW) | (kW) | (kW) | Continuous/Peak |
|---|---|---|---|---|
| Liquid cooling off | 0.00 | 7.25 | 7.25 | Continuous |
| Self-circulation | 0.74 | 7.25 | 7.99 | Continuous |
| 25% cooling | 6.95 | 7.25 | 14.20 | Continuous |
| 50% cooling | 13.90 | 7.25 | 21.15 | Continuous |
| 75% cooling | 20.85 | 7.25 | 28.10 | Continuous |
| Rated cooling | 27.80 | 7.25 | 35.05 | Continuous |
| Rated heating | 24.00 | 7.25 | 31.25 | Continuous |
| Maximum power | 30.00 | 7.25 | 37.25 | Continuous |
| Including transient (fire alarm) | 30.00 | 7.49 | 37.49 | Transient about 3 s |
| Including maintenance/spare sockets | 30.00 | 9.25 | 39.25 | Peak reservation |
Warning
The "core RTE 88.48% (25°C ideal)" given in this report must not be directly used as the on-site acceptance basis. Actual on-site RTE must be based on grid-side + PCS AC-side bidirectional meter readings, and compared after deducting auxiliary consumption per the formulas in this report; otherwise, systematic bias will occur. Actual on-site RTE is typically 0.5-1.5 percentage points lower than the theoretical value due to factors such as ambient temperature deviation from 25°C, battery temperature rise, and auxiliary equipment fluctuation.
Tip
This report estimates single-cycle time based on 0.5P continuous power 2500 kW (approximately 2.0 h charging / 1.8 h discharging). The system nominal power of 25 MW is the PCS peak capability, which significantly differs from 0.5P continuous operation; RTE calculation should clearly follow the continuous power basis to avoid confusion with the peak power basis.
6. Notes
- The energy link in this report is based on the symmetric charge-discharge efficiency assumption under 0.5P conditions. If the actual PCS efficiency deviates significantly across different SOC/power segments, segmented re-fitting should be performed.
- Core RTE 88.48% is the theoretical upper limit under 25°C most ideal conditions, corresponding to the series efficiency of step-up transformer 0.99², battery DC RT 0.94, and PCS 0.98². Actual on-site RTE will degrade item by item due to battery temperature rise (>25°C), line losses, SoH degradation (<100%), etc.
- Liquid cooling unit cooling/heating duty cycles differ significantly at different ambient temperatures; RTE should be calculated within the protocol temperature range.
- DC round-trip efficiency decreases with battery aging; RTE calculation should simultaneously introduce an SOH correction factor.
- If dehumidifiers are started/stopped on demand rather than continuously running at 120 W, the fixed term in the formula should be replaced with the actual duty cycle.
- All power/energy values are single-cycle statistical values and cannot be directly extrapolated to daily/monthly data.
- Container @25°C 0.5P measured liquid cooling power (about 23 kW) + fixed 7.25 kW ≈ 30.5 kW total power.
- Fire protection system includes fire host 200 W continuous monitoring power; explosion-proof exhaust fan 240 W starts only on alarm and is not included in RTE statistics; emergency water firefighting main circuit (fire pumps, sprinklers, etc.) is not included; actual projects equipped with such must supplement (typically 5 – 10 kW), and the main breaker D100A total load capacity must be verified or an independent branch added.
- Six AC dehumidifiers (780 W) run continuously, accounting for 10.8% of total auxiliary. It is recommended to decide start/stop based on ambient humidity sensor data; on-demand operation can recover about 0.2 percentage points RTE.
- Maintenance socket and spare socket (each 1 kW) are peak reservations, not included in the RTE continuous auxiliary model; however, on-site use should be metered separately to avoid affecting RTE protocol reconciliation.
Appendix A Symbol Definitions
A.1 System Parameters
| Symbol | Meaning | Value / Unit | Source |
|---|---|---|---|
| Number of battery clusters | 12 | 1 | |
| Rated capacity per cluster | 418 kWh | 1 | |
| System continuous operating power (0.5P) | 2500 kW | 5.3 | |
| Energy storage container rated battery capacity | 5016 kWh | 1 | |
| $DoD$ | Depth of discharge | 0.95 (95%) | 1 |
| Single-cycle usable battery energy | 4765.2 kWh | 5.1 |
A.2 Efficiency and Baseline Energy
| Symbol | Meaning | Value / Unit | Source |
|---|---|---|---|
| Step-up transformer efficiency (one-way) | 0.99 (99.0%) | 1 | |
| Step-up transformer efficiency (two-way = 0.99²) | 0.9801 (98.01%) | 1 | |
| PCS two-way inverter efficiency (symmetric charge/discharge) | 0.98 (98.0%) | 1 | |
| Battery DC round-trip efficiency (symmetric) | 0.94 (94.0%) | 1 | |
| Battery DC charging efficiency (symmetric split) | 0.9696 (96.96%) | 5.1 | |
| Battery DC discharging efficiency (symmetric split) | 0.9696 (96.96%) | 5.1 | |
| Core RTE (25°C ideal conditions, including TR × PCS × DC RT) | 0.8848 (88.48%) | 5.1 | |
| Baseline grid input energy (excluding auxiliary) | 5065.7 kWh | 5.1 | |
| Baseline AC gross output energy (excluding auxiliary) | 4482.0 kWh | 5.1 |
A.3 Time and Auxiliary Power
| Symbol | Meaning | Value / Unit | Source |
|---|---|---|---|
| Single 0.5P charging time | 2.026 h | 5.3 | |
| Single 0.5P discharging time | 1.793 h | 5.3 | |
| Fixed auxiliary power (project electrical design list total 14 items) | 7.25 kW | 1.1, 5.4 | |
| Single-cluster high-voltage box AC-DC SMPS power | 350 W | 1.1 | |
| Single-cluster high-voltage box DC-DC SMPS power (enabled when AC fails) | 200 W | 1.1 | |
| Distribution box 24 V SMPS power | 480 W | 1.1 | |
| Distribution box 48 V SMPS power | 120 W | 1.1 | |
| Single AC dehumidifier GCH-8120S actual power | 130 W | 1.1 | |
| Number of dehumidifiers | 6 | 1.1 | |
| Total dehumidifier power | 780 W | 1.1 | |
| Industrial air conditioner power | 240 W | 1.1 | |
| Single-cluster BMS power supply power (UPS backed) | 60 W | 1.1 | |
| 12 cluster BMS power supply total power | 720 W | 1.1 | |
| Fire host K11031M2 continuous monitoring power | 200 W | 1.1 | |
| Explosion-proof exhaust fan CNF-350A (starts on alarm, UPS backed) | 240 W | 1.1 | |
| Video surveillance power supply power | 240 W | 1.1 | |
| 24 V auxiliary power supply power | 120 W | 1.1 | |
| Emergency lighting power | 50 W | 1.1 | |
| Cooling fan power | 50 W | 1.1 | |
| Screen (HMI) power | 50 W | 1.1 | |
| Maintenance socket power (peak reservation) | 1000 W | 1.1 | |
| Spare and socket power (peak reservation) | 1000 W | 1.1 | |
| Total average auxiliary power (liquid cooling + fixed auxiliary) | kW | 5.4 |
A.4 Liquid Cooling Unit
| Symbol | Meaning | Value / Unit | Source |
|---|---|---|---|
| Liquid cooling self-circulation (pump only) electrical input | 0.74 kW | 3 | |
| Rated cooling electrical input @W18/L35 | 27.8 kW | 3 | |
| Rated heating electrical input @Tu=10°C | 24.0 kW | 3 | |
| Liquid cooling maximum electrical input | 30.0 kW | 3 | |
| Cooling power slope | 27.06 kW | 5.3 | |
| Cooling duty cycle | 0 ~ 1.08 | 5.3 | |
| Self-circulation duty cycle | 0 ~ 1 | 5.3 | |
| Liquid cooling single-cycle average power | kW | 5.3 | |
| Liquid cooling instantaneous power (scenario table) | kW | 5.4 | |
| DC cabinet cell maximum temperature (cooling main control signal) | °C | 3.1 | |
| DC cabinet cell minimum temperature (heating main control signal) | °C | 3.1 | |
| Liquid cooling outlet temperature (setpoint/protection signal) | 18 °C | 3.1, 3.2 | |
| Inlet-outlet liquid temperature difference (self-circulation trigger signal) | °C | 3.1 |
A.5 Energy and System-level RTE
| Symbol | Meaning | Value / Unit | Source |
|---|---|---|---|
| Grid input energy including auxiliary | kWh | 5.3 | |
| Grid output energy including auxiliary | kWh | 5.3 | |
| Total auxiliary consumption during charging | kWh | 5.4 | |
| Total auxiliary consumption during discharging | kWh | 5.4 | |
| System-level net RTE (including liquid cooling + fixed auxiliary) | % | 5.3 |
A.6 Symbol Naming Conventions
- Subscript
in/outindicates energy flowing into/out of the grid. - Subscript
ch/disindicates charging/discharging process. - Subscript
auxindicates auxiliary system; subscriptliqindicates liquid cooling. - Subscript
idle/cool/heat/maxindicates liquid cooling operating gear. - Subscript
max/min(bare subscripts) indicates cell maximum/minimum temperature (not power gear). - Greek letter denotes efficiency, denotes duty cycle (note distinction from DoD), denotes difference.