SAT-Energy Storage System On-Site Acceptance Professional Verification Checklist

common.lastUpdated: 2026-09-29

BESS Site Acceptance Test — Professional Checklist

Hoenergy · Overseas Business Division · Technology Center | V1.0 Professional | 2026-07-15

Note: First check the applicable scenarios below. Items marked [ENIRIS] / [Self-built] / [Customer] / [With Meter] / [PV] / [DG] in subsequent sections are conditional items (fill in N/A if not applicable).


Project Basic Information

Item Entry
Product Model
Project Code
Factory Serial Number
Capacity · Power
Date
Inspector

Applicable Scenario Checklist

Hoenergy Proprietary EMS / iSolarCloud ENIRIS Third-Party EMS / SmartgridOne V4.1 Customer-Owned EMS With AC/DC Meter [PV] Photovoltaic Inverter [DG] Diesel Generator
☐ Applicable ☐ Applicable ☐ Applicable ☐ Applicable ☐ Applicable ☐ Applicable

Part A — Hardware Installation

Mandatory Checks · 11 Items

No. Inspection Item Acceptance Criteria Result
A1 Equipment Positioning Positions of the container / PCS / transformer / switchgear match the one-line diagram as built ☐ Pass ☐ Fail ☐ N/A
A2 Foundation & Mounting Levelness ≤ 2 mm/m; M12 bolt tightening torque 45 N·m ±5%; anti-loosening marks applied ☐ Pass ☐ Fail ☐ N/A
A3 Earth Grid Earth connections are reliable ☐ Pass ☐ Fail ☐ N/A
A4 One-Line Verification Field wiring matches the as-built drawings (positions of switches / circuit breakers / instrument transformers) ☐ Pass ☐ Fail ☐ N/A
A5 DC Bus Wiring Battery cluster → BCU → PCS DC positive/negative wiring is correct, with no reverse connection or looseness ☐ Pass ☐ Fail ☐ N/A
A6 AC Bus Wiring PCS → transformer → grid-connection point wiring complies with the design ☐ Pass ☐ Fail ☐ N/A
A7 MV/LV Wiring MV cable terminations are fabricated per code (heat-shrink / cold-shrink / silicone rubber) ☐ Pass ☐ Fail ☐ N/A
A8 Cable Sizing Conductor cross-section / voltage class / temperature class meet the design current-carrying capacity and short-circuit withstand requirements ☐ Pass ☐ Fail ☐ N/A
A9 Crimping & Lugs Crimping torque meets the specification; lugs show no overheating discoloration; torque rechecked ☐ Pass ☐ Fail ☐ N/A
A10 Fire Stopping Cable penetrations through floors / fire walls are sealed with fire-resistant putty / fire-rated boards ☐ Pass ☐ Fail ☐ N/A
A11 Markings & Labels Equipment / circuit / phase / warning labels are complete and bilingual (per project requirements) ☐ Pass ☐ Fail ☐ N/A

Part B — Power Supply Verification

Required Checks · 3 Items

No. Inspection Item Acceptance Criteria Conclusion
B1 Three-Phase Voltage Three-phase line-to-neutral voltage unbalance < 2%, amplitude within ±10% of nominal value ☐ Pass ☐ Fail ☐ N/A
B2 Phase Sequence L1-L2-L3 is positive phase sequence, no reverse phase ☐ Pass ☐ Fail ☐ N/A
B3 Frequency 50 Hz ± 0.5 Hz (or 60 Hz, depending on region) ☐ Pass ☐ Fail ☐ N/A

Part C — Metering & Current Transformers

Conditional item [With Meter] · 6 items

No. Inspection Item Acceptance Criteria Result
C1 AC Meter Install Meter model / accuracy class (0.2S / 0.5S) conforms to design, installation orientation is correct ☐ Pass ☐ Fail ☐ N/A
C2 CT Polarity P1 end faces the power source side, P2 end faces the load side; reverse connection is prohibited ☐ Pass ☐ Fail ☐ N/A
C3 CT Ratio Ratio matches the design (e.g., 1000/5 A, 800/5 A) ☐ Pass ☐ Fail ☐ N/A
C4 CT Wiring s1 connects to meter I+, s2 connects to I−, shield layer grounded at one end only ☐ Pass ☐ Fail ☐ N/A
C5 Meter Reading Compare meter readings with a clamp-type ammeter; error < 2% ☐ Pass ☐ Fail ☐ N/A
C6 Meter Communication Meter data (voltage / current / power / energy) read normally via Modbus / IEC 104 ☐ Pass ☐ Fail ☐ N/A

Part D — EMS & Communication Topology

Multi-scenario condition items [ENIRIS] / [Own] / [Customer] / [PV] / [DG] · 9 items

No. Inspection Item Pass Criteria Result
D1 EMS Hardware in Place Server / Gateway / Industrial PC in place, powered on normally ☐ Pass ☐ Fail ☐ N/A
D2 4G Router / Firewall 4G router installed in place, signal normal, firewall policy allowed ☐ Pass ☐ Fail ☐ N/A
D3 Clock Sync NTP / IEC 104 / GPS time synchronization, time deviation ≤ 1 s (Czech projects use IEC 104 sync) ☐ Pass ☐ Fail ☐ N/A
D4 [ENIRIS] SmartgridOne Point Table SmartgridOne Modbus V4.1 full coverage: SOC / SOH / V / T / P / Alarms / Protection ☐ Pass ☐ Fail ☐ N/A
D5 [Own] Hoenergy EMS Point Table iSolarCloud-style EMS connects to PCS / BMS / Meter / Weather Station ☐ Pass ☐ Fail ☐ N/A
D6 [Customer] Third-Party EMS Integration Provide data dictionary per interface protocol and complete communication interface test ☐ Pass ☐ Fail ☐ N/A
D7 Remote Access VPN Owner / dispatch VPN tunnel established, remote login available ☐ Pass ☐ Fail ☐ N/A
D8 [PV] PV Inverter Integration Sungrow / Huawei and other inverters connected to EMS, points complete (DC / AC / Power / Status) ☐ Pass ☐ Fail ☐ N/A
D9 [DG] Diesel Genset Integration Diesel genset controller (ComAp / DeepSea) Modbus integration, including Start-Stop / Paralleling / Power / Status ☐ Pass ☐ Fail ☐ N/A

Part E — Station Build

Mandatory Checks · 6 Items

No. Inspection Item Acceptance Criteria Result
E1 EMS Create Site Create a site in the EMS (iSolarCloud / SmartgridOne / Customer System) and fill in the project information ☐ Pass ☐ Fail ☐ N/A
E2 Device Registration PCS / BMS / Meter / Weather Station / Fire Protection / HVAC all registered ☐ Pass ☐ Fail ☐ N/A
E3 Point Mapping Mapping of the 4 point categories — telemetry, telesignal, telecontrol, and teleadjust — completed (per the point list) ☐ Pass ☐ Fail ☐ N/A
E4 Topology EMS topology diagram auto-generated and consistent with the on-site single-line diagram ☐ Pass ☐ Fail ☐ N/A
E5 [PV] PV Inverter Registration PV inverter registered in the EMS with the communication link established ☐ Pass ☐ Fail ☐ N/A
E6 [DG] Diesel Generator Registration Diesel generator registered in the EMS with the start/stop and paralleling control links established ☐ Pass ☐ Fail ☐ N/A

Part F — Energization & Grid Connection Test

Mandatory Checks · 5 Items

No. Inspection Item Acceptance Criteria Result
F1 Auxiliary Power Energization Lighting / socket / control power energized normally ☐ Pass ☐ Fail ☐ N/A
F2 Control Power Energization BMS / PCS / fire protection / HVAC control power energized ☐ Pass ☐ Fail ☐ N/A
F3 First Grid Connection Close the AC circuit breaker; PCS connects to grid smoothly without inrush ☐ Pass ☐ Fail ☐ N/A
F4 No-Load / Light-Load Run No-load run for 5 min, light-load (10% of rated) run for 5 min ☐ Pass ☐ Fail ☐ N/A
F5 [DG] Diesel Generator Paralleling / Black Start Coordination between diesel generator and energy storage: paralleling / disconnection / black start test, switching time < 2 s ☐ Pass ☐ Fail ☐ N/A

Part G — Cloud Platform Charge/Discharge Test

Must-check · 4 items

No. Inspection Item Pass Criteria Result
G1 Cloud Platform Login Owner / O&M personnel log in to the cloud EMS via browser ☐ Pass ☐ Fail ☐ N/A
G2 Manual Charge Cloud issues a charge command (set power / duration), PCS responds within ≤ 2 s ☐ Pass ☐ Fail ☐ N/A
G3 Manual Discharge Cloud issues a discharge command, PCS responds within ≤ 2 s ☐ Pass ☐ Fail ☐ N/A
G4 Emergency Stop (E-Stop) Cloud emergency stop command response within ≤ 1 s, PCS stops immediately ☐ Pass ☐ Fail ☐ N/A

Part H — Schedule / Planned Curve Test

Mandatory Inspection · 5 Items

No. Inspection Item Pass Criterion Conclusion
H1 Daily Schedule Upload EMS imports a 24 h planned curve (CSV / manual input) ☐ Pass ☐ Fail ☐ N/A
H2 Auto Tracking The system automatically charges and discharges according to the curve without manual intervention ☐ Pass ☐ Fail ☐ N/A
H3 Multi-Period Switching At least 4 periods (Peak / Flat / Valley / Sharp), with smooth switching and no abrupt jumps ☐ Pass ☐ Fail ☐ N/A
H4 Schedule Deviation Actual power vs. planned deviation ≤ 3% (15 min average) ☐ Pass ☐ Fail ☐ N/A
H5 [PV+DG] PV-Storage-DG Coordination Test Linked mode: PV prioritized for self-consumption → energy storage charging → DG backup, with smooth switching ☐ Pass ☐ Fail ☐ N/A

Part K — Fire & Safety

Mandatory Check · 1 Item

No. Inspection Item Pass Criteria Result
K1 E-Stop Button E-Stop buttons at entry/exit are securely installed and easy to operate ☐ Pass ☐ Fail ☐ N/A

Punch List — List of Outstanding Issues

Required to be closed within 30 days

No. Outstanding Issue Severity Responsible Party Closure Deadline
1 ☐ Critical ☐ Major ☐ Minor
2 ☐ Critical ☐ Major ☐ Minor
3 ☐ Critical ☐ Major ☐ Minor
4 ☐ Critical ☐ Major ☐ Minor
5 ☐ Critical ☐ Major ☐ Minor
6 ☐ Critical ☐ Major ☐ Minor

Signatures

Three-Party Closure

Unit Name Signature Date
Hoenergy Engineer
Owner Representative
EPC Supervisor

Summary

Total Items Pass Fail N/A Pass Rate Result

Hoenergy Overseas Business Division Technical Center · V1.0 Professional · 2026-07-15